Mosque construction stages
Back to homeThe path to completion
Mosque project progress
Based on the chart supplied by the community; its measurement date is not specified.
32.3%
Actual cumulative progressAbout these figures
Source: charts supplied by the community. The data update date is not specified in the charts. Some figures differ between the supplied table and charts. This section uses chart figures only.
PlannedActual
| Planned | Actual | |
|---|---|---|
| Annual progress in 1405 | 18.5% | 16.6% |
| Cumulative progress through 1405 | 37.5% | 32.3% |
Construction stages
Transcribed from the supplied table. A dash means no percentage was provided. These figures differ from the earlier chart and are shown separately.
| Stage | Activity | Progress |
|---|---|---|
| 1 | Mosque-centred complex project | 32.36% |
| 1.1 | Concrete structure, domes and minarets | 92% |
| 1.1.1 | Excavation and site levelling | 100% |
| 1.1.2 | Stone masonry | 100% |
| 1.1.3 | Blinding concrete | 100% |
| 1.1.4 | Foundation reinforcement | 100% |
| 1.1.5 | Foundation formwork | 100% |
| 1.1.6 | Foundation concrete pour | 100% |
| 1.1.7 | Ground-floor columns | 100% |
| 1.1.8 | Ground-floor slab | 100% |
| 1.1.9 | First-floor columns | 100% |
| 1.1.10 | First-floor slab | 100% |
| 1.1.11 | Second-floor columns | 100% |
| 1.1.12 | Second-floor slab | 100% |
| 1.1.13 | Main mosque dome structure | — |
| 1.1.14 | Minaret structures | — |
| 1.1.15 | Entrance dome structure | — |
| 1.1.16 | School-side dome structure | — |
| 1.1.17 | Guesthouse-side dome structure | — |
| 1.1.18 | Courtyard structure | — |
| 1.2 | Architecture | 0.46% |
| 1.3 | Building services | — |
| 1.4 | Electrical works | — |
| 1.5 | Building facade | — |